Moving PowerVault 220S to a new PERC

I would like to move my PV220s from the existing PERC3/QC controller to a new PERC4/DC in the same NAS device (PV 755) without losing any data. Can this be done?

 

Thanks.

  • Tariq Syed

    32 Posts

    249

    0

    Posted June 28th, 2004 08:00

    • Make sure you have a complete backup.
    • PERC controller driver and firmware (on both controllers) MUST be at their latest versions
    • PV220S has a firmware that can updated through OpenManage Array Manager. Make sure it is at E17.

    After doing above, you should be fine as long as you write down the drive configuration info (from CTRL M at boot-up, Configure > View/Add Configuration).

    After you shut down server and PV220S, disconnect cable and attach it to the other controller, you should enter CTRL M and go to Configure > View/Add Configuration menu to ensure that drives are tagged exactly as they are. Under ideal circumstances, you should get a submenu that gives your two choices "READ FROM NVRAM OR READ FROM DISKS). You should choose READ FROM DISKS. If they show READY or FAILED, you'll have to retag them. The process of retagging is just like creating a new array MINUS drive initialization.

    If what I have just said, doesn't make much sense, I would recommend getting help from someone who's familiar with PERC controller BIOS.

    Message Edited by Tariq Syed on 06-28-2004 05:02 AM

  • c5thunder

    3 Posts

    249

    0

    Posted June 29th, 2004 02:00

    Thanks for the reply. I am very familiar with the PERC controllers, but i still wanted to make sure. I also forgot to include a very important part of my question...

    Per Dell's documentation, to move a disk enclosure to a new controller without losing data, the enclosure MUST be attached to the same Channel ID on the new controller (i.e. if it was on Channel1 on the old PERC, then it must connect to Channel1 on the new PERC). Since i'm moving from a QC card (4 channels) to a DC card (2 channels), and my PV220 is on Channel3, i dont have many options with regards to preserving the data (except backup/restore).

    The only other option that i could think of is to connect the PV220 to Channel0 or Channel1 on the old PERC, save the configuration, and then migrate over to the new PERC using the same Channel. This should work and i'll find out this weekend.

    I believe i just answered my own question thanks to some PERC documentation that came with the new PERC4/DC, but i thought i'd post it anyway for others to read/comment/correct.

  • Tariq Syed

    32 Posts

    249

    0

    Posted June 29th, 2004 21:00


    I don't think you need to perform that extra step of connecting from Channel 3 to Channel 2 just to move it over to the another controller. There are many ways of doing it and I guess the documentation is simply providing a "caution" so people won't mix up when both channels are used, for example. However, if this extra step makes you feel more comfortable, go for it.

     

  • c5thunder

    3 Posts

    249

    0

    Posted June 30th, 2004 03:00

    If the configuration stored on the Disk includes Channel ID, then this appears to be my only choice since it will update the on-disk configuration prior to the controller upgrade. I will be doing it since i really dont feel like restoring 800GB of data.

    Thanks.