In our efforts to clean up the forum, we came across you question /statement. If the question/statement is still valid , not expired and if you need an update please reach out again and we will try to get it answered.
As part of your migration from the MDS 9513 to MDS 9396, will you be creating an ISL between the 2 switch in order to import the existing Zoning from the MDS 9513 and the new MDS 9396.
You can create ISL between old and new switch to avoid additional task to create port connectivity document (hope you use Soft Zoning). ISL will import all existing config to new switch. After Config merge you can move cables to New switch and disconnect old switch.
healyj
141 Posts
4127
0
Posted May 9th, 2018 03:00
Hi There,
In our efforts to clean up the forum, we came across you question /statement. If the question/statement is still valid , not expired and if you need an update please reach out again and we will try to get it answered.
As for now we will set it to 'answered'
Thanks and rgds,
Jim.