Can we set a SyncIQ policy to run more than 24 hours

Hi All,

I would like to set a SyncIQ policy to run for 44 hours. How would I be able to do that?

Also,

If I need to create a SyncIQ policy which needs to be run twice a day.

Example: I have a policy named IFS_prod and need to run this at 6 AM and 6 PM on the same day. How will I be able to achieve this.

Thanks in advance

Thank you.

  • Peter_Sero

    6 Operator

    •

    1169 Posts

    725

    1

    Posted March 12th, 2018 03:00

    https://www.emc.com/collateral/TechnicalDocument/docu65068.pdf


    page 303:

    If you configure a replication policy to run more than once a day, you cannot configure the interval to span across two calendar days. For example, you cannot configure a replication policy to run every hour starting at 7:00 PM and ending at 1:00 AM.

  • ambikkB

    3 Posts

    725

    0

    Posted March 12th, 2018 21:00

    Hi Peter,

    Thank you for the assistance.

    If I need to create a SyncIQ policy which needs to be run twice a day.

    Example: I have a policy named IFS_prod and need to run this at 6 AM and 6 PM on the same day. How will I be able to achieve this.

    Thanks in advance

  • crklosterman

    450 Posts

    725

    0

    Posted March 13th, 2018 08:00

    Think about it differently. If you run a SyncIQ incremental, how long does it take to run right now?  Let's say for instance that you set it up to run once every 48 hours, and it completes in 40.  Does that mean you couldn't run it daily?  Well, assuming a constant change rate, you could have it run once per day, and it would likely take 20 hours to run. Does that mean you can't run it twice a day?  No, again assuming a constant rate of change, and ignoring for a moment job overhead (starting/stopping), if you ran it every 12 hours, it'd likely complete in 10.  Incremental passes are just block level changes once the first full completes.  Also you may be wasting cycles if you setup the SyncIQ policies too high up in the tree, you could set them up one level deeper and perhaps have better luck.  But that means either deleting all the target data, or setting up the new synciq policies with --target-aware-initial-sync yes.  That's a CLI only option.

    ~Chris

  • SKT2

    2 Intern

    •

    1340 Posts

    725

    0

    Posted March 14th, 2018 02:00

    select Run Multiple Policies Per specified Day during the policy creation  or while editing an existing policy. I ran it every 6 hours. In your case it is every 12 hours. give starting at 0600 AM and end at 11:59 PM