UNSOLVED
delay all backup jobs
hello. my avamar proxy was not properly commiting snapshots so i have several vms with 30+ snapshots present. i am currently in the process of cleaning up all these snapshots. i don't want any new jobs kicking off until this is complete. can someone point me in the right direction so that i can delay the jobs from kicking off? thanks in advance!
cheers.
Responses (1)
Solutions (0)

Sandeep_Sinha
307 Posts
184
0
Posted December 29th, 2011 02:00
Hello,
If you need to prevent all the scheduled jobs from kicking off, then just stop the backup scheduler using the command :
dpnctl stop sched
You can again start the backup scheduler using the command :
dpnctl start sched
Thanks.