RM 5.2.2 and Solutions Enabler upgrade from 6.5.3 to 7.1 or 7.2 with CX4-480
and CX3-80
Hi All,
We have RM 5.2.2 and Solutions Enabler 6.5.3 configured in CX4-480 and CX-380. And now we are planning to upgrade the Solutions Enabler from 6.5.3 to 7.1 or 7.2 (All Host are in Windows 2008 x64bit)?
I just want to know if there is any pre-requisite to do that or can we upgrade Solutions Enabler straight away to 7.1 or 7.2 then do the Enabler patch?
One more thing, our CX4-480 with Flare 28.000.5.706 and CX3-380 (Flare 26 rev. 080) will be able to support this new Solution Enabler 7.1 or 7.2.
For RM and Solutions Enabler compatibility, please refer to the following KB article.
emc212416: "Replication Manager: Need to check compatibility between Replication Manager and Solutions Enabler."
The proper integration with Replication Manager and the supported version(s) of Solutions Enabler is important and this KB is regularly updated as a result.
Currently our CX4-480 flare still at Flare 4.28.000.5.706 and may take time to upgrade to later version of flare but we are considering now to upgrade the Solutions Enabler from 6.5.3 to 7.1 inline with the power path software upgrade rollout. Now with Flare 4.28.xxx.706 and target Solutions enabler 7.1 will work together, thinking of that CX Flare will only takes place may be in 2-3 weeks time after the Solutions Enabler upgrade. FYI, We are upgrading the Solutions Enabler in preparation for RM uprade as well from 5.2.2 to 5.2.3 or to 5.2.x
Please remember to mark the question as Answered when you get the correct or best answer. Also, please award points to the person providing the best answer.
Currently our CX4-480 flare still at Flare 4.28.000.5.706 and may take time to upgrade to later version of flare but we are considering now to upgrade the Solutions Enabler from 6.5.3 to 7.1 inline with the power path software upgrade rollout. Now with Flare 4.28.xxx.706 and target Solutions enabler 7.1 will work together? thinking of that CX Flare will only takes place may be in 2-3 weeks time after the Solutions Enabler upgrade. FYI, We are upgrading the Solutions Enabler in preparation for RM uprade as well from 5.2.2 to 5.2.3 or to 5.2.x.
*****
It was stated above that SE 7.1 supports Flare 30 but no direct information if this will support our current Flare 28.
I couldn't find in powerlink, appreciate if someone has experience or can give more information.
RFritz11
2 Intern
•
244 Posts
332
0
Posted August 17th, 2011 06:00
Hello, We have moved your question to the CLARiiON Support Forum where you should receive prompt attention. Thanks.