How to make 3 copies from BCV

Friends,

I have q question, it might be a basic one for you

I need to make a BCV copy of production data and import into
a test server.Then from this BCV copy restore the data into three
setof database devices.These three will be different copies of the
same data used for different purposes.

A simple pictorial representation of what I want is below.


Prod        |    Test
Host        |    Host
==============================
[PRD]      |    [BCV] --> [COPY 1]
               |             --> [COPY 2]
               |             --> [COPY 3]


Can I have your suggestions on how to make these three copies in test host
from the BCV copy?

thanks in advance
Jayan
  • dynamox

    11 Legend

    •

    20419 Posts

    •

    87439 Points

    1713

    0

    Posted February 9th, 2010 05:00

    as long as you are ok with doing full re-establish on your STD-BCV relationship (plus if your BCV is an RDF1-BCV ..that also means full SRDF re-establish), first i simply cancel relationship. My devices are in a disk group so i run:

    symmir -g cancel

    and tha'ts it. At this point you can use BCVs as your source for TimeFinder operations.

    I did try another approach where i would take a snapshot of my BCV and then i would restore this snapshot to a different device. Performance was horrible, it would take 2 hours to restore 8.6g device. So for now i dont' have a choice but to cancel relationship, clone my BCV to other devices, once clone is complete i terminate clone session and run full-establish on BCVs and then full SRDF sync.

  • dynamox

    11 Legend

    •

    20419 Posts

    •

    87439 Points

    1713

    1

    Posted January 29th, 2010 03:00

    will you need to re-establish BCV back to STD and how often ? We've had similar requirement for while where we need to make copies of RAID-5 BCV to dev and qa environment. Unfortunately BCV can not be source and target of TimeFinder/Clone operation at the same time (V-Max offer cascaded clone where you can do that). So for us in order to do what you are trying to do we always have to cancel STD-BCV relationship and then clone BCV to dev/qa instances. This is very inconvinient for us because our database is around 5 terabytes so every time we cancel STD-BCV relationship, it's a full sync the next time we establish STD-BCV. I have not tried this scenario where BCVs are regular 2-way-mirror or unprotected.

  • Quincy561

    1281 Posts

    1715

    1

    Posted January 29th, 2010 08:00

    Do the 2 copies have to be a copy of a copy?  Why not just make three seperate copies at the same time?   SNAP might be great for this if you can simply make three copies at the same point in time.
  • Jayan3

    10 Posts

    1715

    0

    Posted January 29th, 2010 08:00

    Yeah, ,we will need to establish the STD-BCV pair atleast once in a month or so. Not sure ,how the "cancelling STD-BCV" pair going to work.But waiting to see, if I can get some more suggestions on this.I remember in my previous organisation using some unix "dd" based solution. It may not work ,if data runs in to terabytes.
  • Quincy561

    1281 Posts

    1715

    1

    Posted January 29th, 2010 10:00

    Couldn't you simply make 3 Clone or SNAP copies and make the same modifications to each?

  • Jayan3

    10 Posts

    1715

    0

    Posted January 29th, 2010 10:00

    Yes , they need to be a copy of copy. Becuase after making the first copy(ir BCV), there is going to be some modifications on to it.Only after that , other copies are to be made.

  • Jayan3

    10 Posts

    1715

    0

    Posted February 9th, 2010 01:00

    Hi Dynamox, you have replied that

    "We've had similar requirement for while where we need to make copies of RAID-5 BCV to dev and qa environment. Unfortunately BCV can not be source and target of TimeFinder/Clone operation at the same time (V-Max offer cascaded clone where you can do that). So for us in order to do what you are trying to do we always have to cancel STD-BCV relationship and then clone BCV to dev/qa instances. This is very inconvinient for us because our database is around 5 terabytes so every time we cancel STD-BCV relationship, it's a full sync the next time we establish STD-BCV."

    Can you give little elaboration on this,I mean step by step using commands ? Are you saying you userd the symmir -cancel option. I have never used this options any time. Also I am not sure ,if there is another way exist to accomplish what I am looking for

  • Jayan3

    10 Posts

    1715

    0

    Posted February 9th, 2010 01:00

    No, it is a very time consuming process .I need to make a copy (BCV) of the original data ,then make modifications on to this BCV data and then copy this modifies data to three different set of disks. that is what I want. Any idea on this particular requirement