kally2_0a4338

updated

14 years ago

0

6874

February 27th, 2013 10:00

How to migrate QUORUM disk in W2K3 cluster?

Hi All,Iam planning to migrate CX-3 TO VNX using PPME in W2K3 cluster . Is there any procedure to Migrate Quorum Disk?

  • dynamox

    11 Legend

    •

    20419 Posts

    •

    87439 Points

    1417

    0

    Posted February 27th, 2013 10:00

  • Maliboo74

    89 Posts

    857

    0

    Posted February 27th, 2013 10:00

    Dynamox is correct.  The quorum is not eligible for a PPME migration.  You need to replace the quorum with a disk on the new array. 

  • 1417

    0

    Posted February 27th, 2013 11:00

    1. Start Cluster Administrator (CluAdmin.exe).
    2. Right-click the cluster name in the upper-left corner, and then click Properties.
    3. Click the Quorum tab.
    4. In the Quorum resource box, click a different disk resource.
    5. If the disk has more than one partition, click the partition where you want the cluster-specific data to be kept, and then click OK.          This is the procedure for W2K3 Cluster?
  • Maliboo74

    89 Posts

    1417

    1

    Posted February 27th, 2013 11:00

    Yes.You can check emc268683 for links to both 2003 and 2008 clusters.

  • 1417

    0

    Posted February 27th, 2013 12:00

    Tnx .. I need to do any changes  on the server side after change the Quorum Disk ? I can Place a New Quorum Disk from TGT Array Before Start the PPME Migration ?

  • 1417

    0

    Posted February 27th, 2013 12:00

    Tnx .. I need to do any changes  on the server side after change the Quorum Disk ?

  • dynamox

    11 Legend

    •

    20419 Posts

    •

    87439 Points

    1417

    0

    Posted February 27th, 2013 12:00

    nope, you will need to remove that LUN form CX3 side and clean up PowerPath (powemt check)

  • dynamox

    11 Legend

    •

    20419 Posts

    •

    87439 Points

    1418

    0

    Posted February 27th, 2013 12:00

    you can do quorum change anytime

  • dynamox

    11 Legend

    •

    20419 Posts

    •

    87439 Points

    1122

    0

    Posted February 27th, 2013 13:00

    1) present  quorum drive to both nodes and perform the procedure to swap the quorum (both nodes were online)

    2) move all resources to one node and shutdown the other one(s)

    3) start PPME procedures to migrate the other data drives.

    4) once PPME handles are deleted, remove CX3 storage, clean PowerPath and bring other nodes online (make sure they can see VNX storage)

  • 1417

    0

    Posted February 27th, 2013 13:00

    1) Shut down the Passive node 2) Allocate Tgt luns (VNX) 3) Place the New TGT (VNX) Quorum Disk 4) Start the Migration For all Data Luns 5) Complete Sync 6) Cleanup all old Luns  , here I can take out OLD QUORUM (CX-3)  7) Take out all dead paths in PP 8) bring up the Passive node 9) Failover , Failback For check Cluster Health .............All the Above steps looks good need Any changes Dynamox?